Cook has done this.
David Goff Reactor Engineer Donald C. Cook Nuclear Plant 269-465-5901 x1465
From: Adina K Lafrance adina.k.lafrance@dom.com To: "RETAQS (pwrrm@retaqs.com)" pwrrm@retaqs.com, Cc: Andrew Nicholson andrew.nicholson@dom.com Date: 07/03/2013 11:33 AM Subject: [Pwrrm] Startup Flux Maps Sent by: "PWRRM" pwrrm-bounces@retaqs.com
All,
Does anyone use Westinghouse White Paper to defer startup flux mapping to 50%? Or planning to use the White Paper? (also in WCAP 16303-P Appendix B)
Thank you.
Adina LaFrance Lead Reactor Engineer Surry Power Station
Dominion Generation Phone: 757-365-2658; Internal: 8-798-2658 E-mail: Adina.K.LaFrance@dom.com