- When does your organization issue
the COLR to the Plant (e.g., as needed, before the start of the outage, 3
months prior to the outage) ? The COLR is normally
accepted by our Safety Review team prior to the outage (2-3 weeks).
The procedures that are updated are posted during the outage.
Additionally, any changes during the cycle are processed as needed.
- How
long after issuance to the Plant is the COLR sent to the NRC? We generally
send the COLR to licensing shortly after it is approved (within a week of
approval). Licensing then has to write a cover letter and send the
letter around for review and signature before it is sent to the NRC (this
typically takes a week or two). Per RMD - We are supposed to
send the COLR to licensing about 2 weeks after shutdown. We are
supposed to verify that licensing has transmitted the approved COLR to the
NRC 90 days after shutdown.
- What
organization prepares and issues the COLR (e.g. core design, safety
analysis, licensing, etc.)? Our fuel projects group
prepares and issues the COLR. Because it is a report and not as
easily accessible at the site level, Reactor Engineering then updates a
Design Reference Procedure that anyone at the site can access. We
update the DRP during the outage (as noted above).
Adina
LaFrance
The significant problems we face cannot be solved at the same
level of thinking we were at when we created them. -Albert Einstein
Nuclear
Analysis & Fuel
Reactor
Engineer
Surry
Power Station
Email:
Adina.K.LaFrance@Dom.com
Phone:
757-365-2658
Pager
#: 4290
From: pwrrm@retaqs.com
[mailto:pwrrm@retaqs.com] On Behalf Of Gore, Duane
Sent: Tuesday, January 05, 2010 3:15 PM
To: 'PWR Reactivity Management'
Subject: [Pwrrm] Issuance of the COLR
We
have been questioned by our Resident as to the timeliness of issuing the Core
Operating Limits Report (COLR). We issue it after we approve our Reload Safety
Evaluation report. Sometimes this is done before the refueling outage starts,
other times it is just prior to core reload. Other than having it in place when
the new core is loaded, we do not have any requirements on a lead-time. When we
issue the COLR to the Plant we also issue it to Licensing and they do the
formal transmittal to the NRC.
- When does your organization issue
the COLR to the Plant (e.g., as needed, before the start of the outage, 3
months prior to the outage) ?
- How long after issuance to the
Plant is the COLR sent to the NRC?
- What organization prepares and
issues the COLR (e.g. core design, safety analysis, licensing, etc.)?
Thank
you in advance for your responses.
Duane
Gore
Supervisor,
Reactor Engineering
STPNOC
(361)
972-8909