REG response below:

 

Request for industry peer feedback – I have the following 3 questions:

Does your site / utility account for washout or tramp SNM that may collect throughout the plant? No

If you do account for the SNM, do you estimate the amount or use a method to quantify the amount? N/A

Do you report the loss (as inadvertent losses or otherwise) on DOE/NRC form 742 or other forms? No

 

 

Andrew Kelliher

Reactor Engineer

R.E. Ginna Nuclear Power Plant

Phone: (585) 771-3457

 

"I'm just sayin', I don't like fun." - Karl Pilkington

 

From: pwrrm@retaqs.com [mailto:pwrrm@retaqs.com] On Behalf Of MCKINNEY, MICHAEL R
Sent: Tuesday, September 13, 2011 8:22 PM
To: pwrrm@retaqs.com; respvr@retaqs.com
Subject: [Pwrrm] SNM from fuel leaks

 

Request for industry peer feedback – I have the following 3 questions:

Does your site / utility account for washout or tramp SNM that may collect throughout the plant?

If you do account for the SNM, do you estimate the amount or use a method to quantify the amount?

Do you report the loss (as inadvertent losses or otherwise) on DOE/NRC form 742 or other forms?

 

Entergy has had fuel leaks in the past and one fuel leak currently.

Trace amounts of Special Nuclear Material (SNM) may be present in the reactor coolant, clean-up, and/or rad waste systems due to present or past fuel failures. 

The SNM is difficult to measure in the coolant system and therefore cannot be accounted for. 

But this SNM may be quantified in rad waste prior to disposal. 

Entergy Nuclear's fleet SNM Control program does not currently address the accounting treatment of this SNM.

 

Thanks,

Mike

 

Michael R. McKinney

Supervisor, PWR Fuels

mmckinn@entergy.com

601-368-5450

 

 

 

>>> This e-mail and any attachments are confidential, may contain legal,
professional or other privileged information, and are intended solely for the
addressee.  If you are not the intended recipient, do not use the information
in this e-mail in any way, delete this e-mail and notify the sender. CEG-IP2