This is what we use for the Dominion Units (Surry, Kewanee, North Anna and Millstone):

 

3.9 Unplanned Reactivity Change Caused by Equipment Problem or Personnel Error

• Reactor Power Change >0.5% RTP When >5% RTP

• Reactivity Change >350 pcm When <5% RTP

 

 

4.6 Unplanned Reactivity Change Caused by Equipment Problem or Personnel Error

• Reactor Power Change < 0.5% RTP When >5% RTP

• Reactivity Change <350 pcm and >150 pcm When < 5% RTP

 

 

Charlene Chotalal

Lead Reactor Engineer

Nuclear Analysis & Fuels, Surry Power Station

 

Dominion Generation

Phone: 757-365-2819; Fax: 757-365-2750

E-mail: Charlene.N.Chotalal @dom.com

 

 

From: pwrrm@retaqs.com [mailto:pwrrm@retaqs.com] On Behalf Of Fago, Carl D
Sent: Wednesday, December 29, 2010 7:53 AM
To: PWR Reactivity Management
Subject: Re: [Pwrrm] values of "x" for PI

 

Here is what Duke Energy (Oconee Nuclear Station, Catawba Nuclear Station, & McGuire Nuclear Station) uses:

 

A positive change in reactivity GREATER THAN OR EQUAL TO:

·         0.05% ÄK/K (50 pcm) beyond intended change or expected tolerance (Mode 2 only) OR

·         0.35% ÄK/K (350 pcm) beyond intended change or expected tolerance (Mode 3, 4, 5, and 6

only)

A negative change in reactivity GREATER THAN OR EQUAL TO 0.15% ÄK/K (150 pcm)

beyond intended change or expected tolerance (Mode 2 only)

 

Carl

 

 

Carl D. Fago

Event Recovery Manager

Oconee Nuclear Station

Duke Energy Carolinas

Phone:  (864) 873-3047

Fax:  (864) 873-3374

Email:  Carl.fago@duke-energy.com

 

 

From: pwrrm@retaqs.com [mailto:pwrrm@retaqs.com] On Behalf Of ddgoff@aep.com
Sent: Tuesday, December 28, 2010 2:53 PM
To: pwrrm@retaqs.com
Subject: [Pwrrm] values of "x" for PI

 


What values of "x" are plants using for example criteria 3.9 and 4.6 in the PWR Reactivity Management Performance Indicator PI?

David Goff
Reactor Engineer
Donald C. Cook Nuclear Plant
269-465-5901 x1465


CONFIDENTIALITY NOTICE: This electronic message contains information which may be legally confidential and/or privileged and does not in any case represent a firm ENERGY COMMODITY bid or offer relating thereto which binds the sender without an additional express written confirmation to that effect. The information is intended solely for the individual or entity named above and access by anyone else is unauthorized. If you are not the intended recipient, any disclosure, copying, distribution, or use of the contents of this information is prohibited and may be unlawful. If you have received this electronic transmission in error, please reply immediately to the sender that you have received the message in error, and delete it. Thank you.