Hopefully, folks have time to answer a few staffing questions.  Thank you!


How many reactor engineers per unit at your site?  What experience level?

Response - 2 Unit Site. 1 Supervisor (qualified), 4 qualified REs - 2 more than 30 years expereince,1 with 5 years experience and 1 with less than 2 years experience. One open position that will be filled with new college graduate

What reactivity management-related duties are there?  For example: plan preparation, control room attendance during maneuvers, run/attend station RM oversight committee.

Response - Plan preparation is all performed by RE for periodic and evolution specific (> 10% planned power changes). Control Room attendance during all >10% planned power maneuvers. RE performs almost all aspects of reactivity management inclduing reviews of CRs, initial categorization of events, PI, meeting coordination and administrative duties.

Other programs or responsibilities you would deem major?  For example: SNM tracking/reporting, plant systems, computer administration.

Response - SNM tracking, inventory and reporting, all fuel move planning, maintain computer/software used to monitor core, no plant systems but support incore and excore issues, support dry cask storage

David Goff
Reactor Engineer
Donald C. Cook Nuclear Plant
269-465-5901 x1465
_______________________________________________
PWRRM mailing list
PWRRM@retaqs.com
http://www.keffective.com/mailman/listinfo/pwrrm

----------------------------------------- The information contained in this message is intended only for the personal and confidential use of the recipient(s) named above. If the reader of this message is not the intended recipient or an agent responsible for delivering it to the intended recipient, you are hereby notified that you have received this document in error and that any review, dissemination, distribution, or copying of this message is strictly prohibited. If you have received this communication in error, please notify us immediately, and delete the original message.