At South Texas Project we provide seven
standard plans and use BEACON to run the load swing calculations. They include
down powers to 90% in 1 hr, 80% in 1 hr, 70% in 1 hr, 60% in 1 hr, 60% in 10
minutes, 40% in 2 hrs, and 0% in 3 hrs. These are provided to our operators
every 2 to 3 weeks for both units.
Kristin Chesson
Reactor Engineering
(361)972-4685
Pager 1620
From:
Adina.K.Lafrance@dom.com [mailto:Adina.K.Lafrance@dom.com]
Sent: Tuesday, September 16, 2008
11:40 AM
To: pwrrm@retaqs.com
Subject: [Pwrrm] Standard Ramp
Plans
Two Questions involving standard ramp plans (the plans
given to ops for common ramping needs- turbine balance shot, misaligned rod,
backing off RTP, securing MFP):
How
many cases are run for the standard ramp plans given to ops? (our sites run
between six per month per unit to 16 per quarter)
How
often are standard ramp plans updated at each site? (we do monthly for two of
our sites, quarterly at the other two)
Adina LaFrance
Nuclear Analysis & Fuel
Reactor Engineer
Surry Power Station
Email: Adina.K.LaFrance@Dom.com
Phone: 757-365-2658
Pager #: 4290
CONFIDENTIALITY NOTICE: This electronic
message contains information which may be legally confidential and/or
privileged and does not in any case represent a firm ENERGY COMMODITY bid or
offer relating thereto which binds the sender without an additional express
written confirmation to that effect. The information is intended solely for the
individual or entity named above and access by anyone else is unauthorized. If
you are not the intended recipient, any disclosure, copying, distribution, or
use of the contents of this information is prohibited and may be unlawful. If
you have received this electronic transmission in error, please reply
immediately to the sender that you have received the message in error, and
delete it. Thank you.