At Oconee Nuclear Station we did
a specific evaluation that looked at all RxE hands-on work and where RxE could
be directing or perceived as directing covered work and concluded that RxE do
not perform covered work activities and are therefore not covered workers. I’ve
attached the matrix we used to make that determination.
Duke had published a system list
which indicated which systems were considered high safety significance for use
in making such determinations.
Hope this helps.
Carl
Carl D. Fago
Reactor Engineering Supervisor
Oconee Nuclear Station
Duke Energy Carolinas
Phone: (864) 873-3047
Fax: (864) 873-3374
Email: Carl.fago@duke-energy.com
From: pwrrm@retaqs.com
[mailto:pwrrm@retaqs.com] On Behalf Of SCHAWE, BARTON P
Sent: Thursday, October 22, 2009 9:14 AM
To: 'pwrrm@retaqs.com'
Cc: SMITH, MICHAEL R
Subject: [Pwrrm] New Work Hour Rules
FCS has implemented the new work hour rules such that
Reactor Engineers are covered workers. Are Reactor Engineers at other plants
considered covered workers?
A quick response would be greatly appreciated. Thanks.
Barton
P. Schawe, P.E.
Principal
Reactor Engineer
Omaha Public Power District
Tel:
402-533-7211
email:
bschawe@oppd.com
This
transmission contains information which may be confidential and which may also
be privileged. It is intended for the named addressee only. Unless you are the
named addressee, or authorized to receive it on behalf of the addressee, you
may not copy or use it, or disclose it to anyone else. If you have received
this transmission in error please contact the sender. Thank you for your
cooperation.
|