We have been questioned by our Resident as to the timeliness
of issuing the Core Operating Limits Report (COLR). We issue it after we
approve our Reload Safety Evaluation report. Sometimes this is done before the
refueling outage starts, other times it is just prior to core reload. Other
than having it in place when the new core is loaded, we do not have any
requirements on a lead-time. When we issue the COLR to the Plant we also issue
it to Licensing and they do the formal transmittal to the NRC.