Kevin S. Elam
Reactor
Engineer
(423)365-8806
Pager 14211
1)
the level of review a plan requires
(such as <10% requires shift supervision, >10% requires shift management,
>50% requires station management)
Any plan > 15% (or at OPS request) where we have more than
6 hours to prepare, requires a formalized plan from Reactor Engineering.
These plans must be approved by the Ops Shift Manager, Control Room SRO, and RO
at the controls prior to commencement.
2)
or
2) when a
reactivity plan must be revised (such as > 1 hour delay, rods > 10 steps
from the predicted value, current power level step >2% from
predicted)
IF
Reactor Engineering
is providing continuous coverage for a maneuver
IF
actual plant
conditions deviate from the guidance by ≥ 3% Rated Thermal Power, maneuver guidance
SHALL be updated per Limit and
Precaution 6.3.1.
IF
control rod position
is within 15 steps of Rod Insertion Limit OR
IF
T-Avg deviates more
than three degrees from prediction or T-Ref at any time step, it is recommended
that maneuver guidance be updated per Limit and Precaution
6.3.2.
Maneuver guidance MAY also be updated at the discretion of
Operations and Reactor Engineering.
Additional question
How do other stations incorporate
any ramp rate restrictions that may apply? (Ramp rate alarm, operator
training, ramp plan)
The ramp rates are
accounted for during the generation of the plan.
Jon-Michael
Vandergriff
Catawba Nuclear
Station
Reactor
Engineering
(803)
701-4029
Rule #113 - Don't look
for opportunities; make them.
From: Keller,
Lee A
Sent: Monday, June 30,
2008 9:33 AM
To: Vandergriff,
Jon-Michael
Subject: FW:
[Pwrrm] Reactivity plan approval and revisions/ramp rate
alarm
Pls
answer.
From:
pwrrm@retaqs.com [mailto:pwrrm@retaqs.com] On
Behalf Of Adina.K.Lafrance@dom.com
Sent: Monday, June 30, 2008 9:20
AM
To:
pwrrm@retaqs.com
Subject:
[Pwrrm] Reactivity plan approval and revisions/ramp rate
alarm
SOER 07-01 recommendation 3 stated
that "plans for significant reactivity changes are reviewed and approved by
appropriate station and shift operations management..." and "If plant conditions
delay power changes, the reactivity plan is revised to meet the new plant
conditions and approved by management".
Does anyone
have specific thresholds for:
1) the level of review
a plan requires (such as <10% requires shift supervision, >10% requires
shift management, >50% requires station management)
or
2) when a
reactivity plan must be revised (such as > 1 hour delay, rods > 10 steps
from the predicted value, current power level step >2% from
predicted)
Additional question
How do other stations incorporate
any ramp rate restrictions that may apply? (Ramp rate alarm, operator
training, ramp plan)
Thank you.
Adina LaFrance
Nuclear
Analysis & Fuel
Reactor Engineer
Surry Power Station
Email:
Adina.K.LaFrance@Dom.com
Phone: 757-365-2658
Pager #: 4290
CONFIDENTIALITY NOTICE: This electronic message contains information which may
be legally confidential and/or privileged and does not in any case represent a
firm ENERGY COMMODITY bid or offer relating thereto which binds the sender
without an additional express written confirmation to that effect. The
information is intended solely for the individual or entity named above and
access by anyone else is unauthorized. If you are not the intended recipient,
any disclosure, copying, distribution, or use of the contents of this
information is prohibited and may be unlawful. If you have received this
electronic transmission in error, please reply immediately to the sender that
you have received the message in error, and delete it. Thank
you.