Do you use Beacon or another similar
program to generate the plans?
Adina LaFrance
Nuclear Analysis & Fuel
Reactor Engineer
Surry Power Station
Email: Adina.K.LaFrance@Dom.com
Phone: 757-365-2658
Pager #: 4290
aburger@firstenergycorp.com Sent by: pwrrm@retaqs.com
09/16/2008 01:23 PM
Please respond to
PWR Reactivity Management <pwrrm@retaqs.com>
To
PWR Reactivity Management <pwrrm@retaqs.com>
cc
Subject
Re: [Pwrrm] Standard Ramp Plans
Beaver Valley Power Station Unit 1 & 2 response:
We provide monthly updates to the periodic Reactivity Plans. The Periodic
Plans contains two parts. The first part provides daily operational
guidance such as the amount of water/acid, and/or rods needed to change
temperature 1F and power by 1%. This information can also be used for power
changes less than 10% such as Tubine Govenor/Throttle Valve testing. The
second part of the Periodic Plan contains information to support any rapid
power reductions. This data includes the boration/rod movement needed to
support 2%/min and 5%/min power reductions for 10%, 20%, 30%, 50% and 75%
power changes. The data also includes dilution data following the various
power changes.
Anthony (A.R.) Burger
Supervisor, Reactor Engineering
FENOC - Beaver Valley Power Station
Phone: (724) 682-4108
Cell: (724) 601-3224
FAX: (724) 682-4250
Email: aburger@firstenergycorp.com
Adina.K.Lafrance@
dom.com
Sent by:
To
pwrrm@retaqs.com
pwrrm@retaqs.com
cc
09/16/2008 12:41
Subject
PM
[Pwrrm] Standard
Ramp Plans
Please respond to
PWR Reactivity
Management
<pwrrm@retaqs.com
>
Two Questions involving standard ramp plans (the plans given to ops for
common ramping needs- turbine balance shot, misaligned rod, backing off
RTP, securing MFP):
How many cases are run for the standard ramp plans given to ops? (our sites
run between six per month per unit to 16 per quarter)
How often are standard ramp plans updated at each site? (we do monthly
for
two of our sites, quarterly at the other two)
Adina LaFrance
Nuclear Analysis & Fuel
Reactor Engineer
Surry Power Station
Email: Adina.K.LaFrance@Dom.com
Phone: 757-365-2658
Pager #: 4290
CONFIDENTIALITY NOTICE: This electronic message contains information which
may be legally confidential and/or privileged and does not in any case
represent a firm ENERGY COMMODITY bid or offer relating thereto which binds
the sender without an additional express written confirmation to that
effect. The information is intended solely for the individual or entity
named above and access by anyone else is unauthorized. If you are not the
intended recipient, any disclosure, copying, distribution, or use of the
contents of this information is prohibited and may be unlawful. If you
have
received this electronic transmission in error, please reply immediately
to
the sender that you have received the message in error, and delete it.
Thank you._______________________________________________
PWRRM mailing list
PWRRM@retaqs.com
http://www.keffective.com/mailman/listinfo/pwrrm
-----------------------------------------
The information contained in this message is intended only for the
personal and confidential use of the recipient(s) named above. If
the reader of this message is not the intended recipient or an
agent responsible for delivering it to the intended recipient, you
are hereby notified that you have received this document in error
and that any review, dissemination, distribution, or copying of
this message is strictly prohibited. If you have received this
communication in error, please notify us immediately, and delete
the original message.
_______________________________________________
PWRRM mailing list
PWRRM@retaqs.com
http://www.keffective.com/mailman/listinfo/pwrrm