This email is being sent out for North Anna Reactor Engineering.
North Anna (3 loop Westinghouse) is planning to replace a PRNI in their
next outage. The question is do other utilities put any special measure in
place for startup due to the new detector? Are your Hi Flux Trips
extremely low? Is the startup performed with the NI channel in TRIP?
Any feedback would be appreciated. Please send your responses to
Robert_A._Wright(a)dom.com.
Nuclear Analysis & Fuel
Lead Reactor Engineer
Surry Power Station
Email: Michael_Fanguy(a)Dom.com
Phone: 757-365-2155
Pager #: 3453
-----------------------------------------
CONFIDENTIALITY NOTICE: This electronic message contains
information which may be legally confidential and/or privileged and
does not in any case represent a firm ENERGY COMMODITY bid or offer
relating thereto which binds the sender without an additional
express written confirmation to that effect. The information is
intended solely for the individual or entity named above and access
by anyone else is unauthorized. If you are not the intended
recipient, any disclosure, copying, distribution, or use of the
contents of this information is prohibited and may be unlawful. If
you have received this electronic transmission in error, please
reply immediately to the sender that you have received the message
in error, and delete it. Thank you.