Mark,
Beaver Valley does not have Tech Spec
BEACON. Additionally, when we converted to Improved Standard Tech Specs
we moved the Incore detector requirements, 75 % and 2 per quadrant, to
the Licensing Requirements Manual from the Tech Specs.
Anthony (A.R.) Burger
Supervisor, Reactor Engineering
FENOC - Beaver Valley Power Station
Phone: (724) 682-4108
Cell: (724) 601-3224
FAX: (724) 682-4250
Email: aburger@firstenergycorp.com
From:
"Mayer, Mark"
<MLM3@pge.com>
To:
"'respvr@retaqs.com'"
<respvr@retaqs.com>
Date:
10/19/2011 12:42 PM
Subject:
[Respvr] BEACON
Topical Question
Sent by:
respvr@retaqs.com
Diablo Canyon has a request for all BEACON
users -
A recent review of our BEACON topical indicates
a potential discrepancy between the BEACON topical and our Technical Specifications.
The issue stems from the number of MIDS thimbles required to be used
during a flux map. The BEACON topical in places states that the required
number of thimbles is 75% with at least four thimbles per quadrant.
Our Tech Specs only require two per quadrant. The draft
COLR in the topical (provided to the NRC in an RAI on the topical) and
the NRC SER on BEACON acknowledges the use of four per quadrant.
We requested approval to use BEACON PDMS
through a license change that did not identify any deviations from the
BEACON topical.
At this time, we have a conflicted licensing
basis and are looking for input from other plants which may have a similar
quandary.
- How many thimbles do you require? (% and
#/quadrant?)
- Do you have a similar issue?
- Did you identify this as a difference between
the topical and your application of BEACON?
- Do you have any other insights to share
with respect to the use of BEACON?
Thanks in advance,
Mark Mayer
Diablo Canyon Power Plant
805-545-4674
_______________________________________________
Respvr mailing list
Respvr@retaqs.com
http://www.keffective.com/mailman/listinfo/respvr
-----------------------------------------
The information contained in this message is intended only for the
personal and confidential use of the recipient(s) named above. If
the reader of this message is not the intended recipient or an
agent responsible for delivering it to the intended recipient, you
are hereby notified that you have received this document in error
and that any review, dissemination, distribution, or copying of
this message is strictly prohibited. If you have received this
communication in error, please notify us immediately, and delete
the original message.