Question for the group...
SOER 07-1 provides the admonition to discourage low power
operation for an extended period of time.
How have you defined “low power operation” and “extended
period of time”?
We’re proposing defining “low power operation”
as operation with the turbine offline. And “extended period of time”
as 24 hours greater than the planned outage schedule (the assumption here is that
the outage planning process has evaluated the risks of operation within the
plan).
Is our proposal more or less conservative than your
equivalent?
Thanks!
Carl