Some questions for the PWR folks:
Do you perform in-core shuffle for
reloads?
If yes ...
- How much time is normally
scheduled for in-core shuffle?
- How many FA in your core?
How many components (burnable poisons, control rods, sources, thimbles,
etc.)?
- Roughly, how many individual
assembly or component moves is your normal reload?
- Do you have an installed mast
for components (I’ve heard that some use a temporary component mast
installed each outage)?
Thanks!
Carl
Carl D. Fago
Reactor Engineering Supervisor
Oconee Nuclear Station
Duke Energy