See attached for Waterford. For preconditioned fuel, normally 30%/hr.
Clint Alday
-----Original Message----- From: respvr-bounces@retaqs.com [mailto:respvr-bounces@retaqs.com] On Behalf Of aburger@firstenergycorp.com Sent: Wednesday, February 20, 2008 8:35 AM To: respvr@retaqs.com Subject: [Respvr] Ramp Rates for Normal Operations
What restrictions do PWRs place on ramp rates for normal operations (fuel already conditioned to 100% power)? This would include extended reduced power operation considerations, i.e. reduced power for X number of days would require further ramp rate restrictions compared to a weekend load swing.
Anthony (A.R.) Burger Supervisor, Reactor Engineering FENOC - Beaver Valley Power Station Phone: (724) 682-4108 Cell: (724) 601-3224 FAX: (724) 682-4250 Email: aburger@firstenergycorp.com
----------------------------------------- The information contained in this message is intended only for the personal and confidential use of the recipient(s) named above. If the reader of this message is not the intended recipient or an agent responsible for delivering it to the intended recipient, you are hereby notified that you have received this document in error and that any review, dissemination, distribution, or copying of this message is strictly prohibited. If you have received this communication in error, please notify us immediately, and delete the original message. _______________________________________________ Respvr mailing list Respvr@retaqs.com http://www.keffective.com/mailman/listinfo/respvr