Oconee is in week #2 of our E&A and a question has
arisen that I could use some benchmarking help with. Specifically, during
offload or reload, who makes the decision to increase / decrease the overload /
underload setpoint (within the fuel vendor handling limits) on the fuel crane? We
have a Refueling SRO on the bridge and a fuel handler (operating the bridge and
mast crane). We let these two make the decision on what’s needed within
strict limits that are provided in technical procedures that they are trained
on. (Any very rate instance that we may need to go outside the vendor limits
would have significantly higher approval level and would involve the fuel
vendor in the decision process ... this would represent an “event”.)
For your fleet / site, do you do something similar? Do you
have a higher level of approval? If you have a higher level of approval
required, how often do you encounter the need to increase / decrease the
setpoint (within the fuel vendor handling specification limits)? Or, perhaps
your overload / underload setpoints are at the vendor limits?
Any quick turnaround answer or a contact name / number would
be very much appreciated!
Carl