Carl,

An Updated Final Safety Analysis Report or TS or COLR change does not require an Engineering Change to implement the process for all LARs

Entergy does use the engineering change (EC) process (the Entergy plant modification process) to approve a reload. The SAR change and COLR change are typically parts of the reload EC, though.

Mike  

 

Michael R. McKinney

Supervisor, PWR Fuel Engineering

mmckinn@entergy.com

601-368-5450 (internal 8-433-5450)

cell 601-832-9635

 


From: respvr@retaqs.com [mailto:respvr@retaqs.com] On Behalf Of Fago, Carl D
Sent: Thursday, July 02, 2009 1:46 PM
To: respvr@retaqs.com
Subject: [Respvr] LAR Implementation

 

Does anyone use the plant modification process (or equivalent) to implement approved LARs that do not result in a physical change to an SSC?

 

Thanks!

 

Carl

 