Yes

 

  1. 144 hours (best ever is 128, best ever for offload-CEA shuffle-reload is 144)
  2. 217, 89 CEAs
  3. 217 + 92 = 319 fuel, 89 CEA
  4. Yes, we have a dual masted refuel machine – one for CEAs and one for fuel (including a fuel assembly with a CEA in it)

 

Clint Alday

Waterford 3

 

-----Original Message-----
From: respvr-bounces@retaqs.com [mailto:respvr-bounces@retaqs.com] On Behalf Of Fago, Carl D
Sent: Friday, December 07, 2007 8:37 PM
To: respvr@retaqs.com
Subject: [Respvr] PWR Core Reload Question

 

Some questions for the PWR folks:

 

Do you perform in-core shuffle for reloads?

 

If yes ...

 

1.       How much time is normally scheduled for in-core shuffle?

2.       How many FA in your core?  How many components (burnable poisons, control rods, sources, thimbles, etc.)?

3.       Roughly, how many individual assembly or component moves is your normal reload?

4.       Do you have an installed mast for components (I’ve heard that some use a temporary component mast installed each outage)?

 

Thanks!


Carl

 


Carl D. Fago

Reactor Engineering Supervisor

Oconee Nuclear Station

Duke Energy

864-885-3047

cdfago@duke-energy.com