From: Bojduj, William [mailto:WXB2@pge.com] Sent: Friday, February 10, 2006 1:26 PM To: peter.moravek@exeloncorp.com; pwrrm-bounces@retaqs.com Subject: Power Ascension Flux Mapping for Westinghouse PWRs
RE folks:
I would greatly appreciate it if you could answer the following three questions for your Westinghouse PWRs:
(1) Do you perform a flux map at ~30% RTP and ~50% RTP?
(2) How long do you stabilize before collecting MIDS data at these plateaus?
(3) What is the basis for the stabilization times?
Best Regards, Bill Bojduj ☺ Diablo Canyon Power Plant Senior Advisory Engineer Reactor Engineering P.O. Box 56 Mail Stop 104/4/4B Avila Beach, CA 93424 805-545-3177 (Fax: 805-545-6992)